Basic House Construction Cost in 2022 – If you have a low budget and want to construct a low Budget basic house than this is the complete estimate of a 1000sqft house for C class construction that gives you an approximate idea about your house construction cost. If you want a pdf of this estimate, pls check the get pdf section of our site.
1000Sqft C Class Basic House Construction Cost in 2022
Construction Cost Percentage
Construction materials cost – 70%
Labor Cost – 30%
Suppose, the total construction cost – Is Rs. 10lakh
So, Materials cost will be – 7lakh
and, Labor cost will be – 3lakh
Remember,
Generally, there are three types of house construction
A class house construction
B class house construction
C class house construction
A class house construction – A class house construction is a premium class house construction in which all branded materials are used. This type of construction is done with the latest equipment & technology & under the supervision of architects and supervisors. These are generally framed structures in which the load building load is carried by columns & beams. Al luxury house construction is coming under the A-class construction category.
B – class house construction – Generally 90% of people go with b – class house construction which is done for modern houses, some branded materials are also used in b – class house construction. It is also a framed structure where the total building load
act on beams & columns. All modern house construction is coming under the B-class construction category.
C – class house construction – This is a simple & basic type of house construction. It is not a framed structure construction. This is a load-bearing construction in which the total load is coming on walls only. There is no beam & columns used in this type of construction. Locally available materials are used in such types of construction.
Each class house construction rates vary from city to city. Here we will discuss C – Class House construction estimation.
1000Sqft House Construction Cost (C class)
Suppose, the total built-up area – is 1000sqft
Today, C class house construction Rates – Rs.1100 to 1200/-sqft
Let’s consider an average rate – 1150/-sqft
So, the total construction cost of a 1000 sqft house with finishing is – 1000 x 1150 = Approx Rs.11.5lakh.
Materials Required For 1000Sqft (2BHK) House Construction
1). Cement (सीमेंट)
Approx Cement quantity – 290Bags
Rate – Rs.310 to330/-bag (Jk Lakshmi, Birla & Shree)
Consider an average rate – Rs.320/-Bag
Total Cement cost – 290 x 320 = Rs.92,800/-
2). Sand (रे ती)
There are two types of Sand mostly used in house construction
Brown Sand Rate – Rs.55 to 60/-Sqft
White River Sand Rate – Rs.65 to 70/-Sqft
Consider Brown Sand & Maximum rate – 60/-Cft
Approx Sand quantity – 1800Cft
Total sand cost – 1800 x 60 = Rs.1,08,000/-
3). Aggregates
There are two types of aggregates mostly used in house construction-
Neelam Rodi Rate – Rs.30/-Cft
Gunwatta Rodi Rate – Rs.27/-Cft
Consider Gunwatta Rodi – 27/-Cft
Approx Aggregates quantity – 1000Cft
Total Aggregates cost = 1000 x 27 = Rs.27,000/-
4). Steel Reinforcement
Approx Steel quantity – 1900kg (1.9mt)
Secondary Steel Rate – Approx Rs.45 to 50/-kg
Total Steel bar cost = 1900 x 50 = Rs.95,000/-
5). Bricks
There are three types of bricks mostly used in house construction –
1st Class Bricks
2nd Class Bricks
3rd Class Bricks
Consider 2nd Class Bricks
Second class Bricks Rate – Approx Rs.5/-Nos.
Approx Bricks Quantity – 34000Bricks
Total Brick cost – 34000 x 5 = Rs.1,70,000/-
Total Civil Works Materials Cost – Cement + Sand + Aggregates + Steel + Bricks
= 92800 + 95000 + 108000 + 27000 + 170000 = Rs. 4,92,800/- or Round off Rs.4,93,000/-
Finishing Materials Quantity Required
1). Flooring Tiles
Approx Tiles quantity – 650Sqft
(Including floor area & skirting)
Consider tile size – of 2′ x 2′
Average Market Rate – Approx Rs.35/-Sqft (Local brands tiles)
Total flooring tiles cost – 650 x 35 = Rs.22,750/-
2). Washroom Tiles
(Consider 2 bathrooms in a 2 BHK house)
No. of washrooms in 2 BHK – 2Nos.
Tiles required in 1 washroom Approx – 150Sqft
Total tiles quantity required – 150 x 2 = 300Sqft
Consider tile size – of 1′ x 1.5′
Average Market Rate – Approx Rs.25 to 30/-Sqft (Local brands tiles)
Total Washroom Tiles Cost – 300 x 28 = Rs.8400/-
3). Granite
Granite required for L – shaped kitchen – 50’
Average market Rate Approx – Rs.100/-Sqft
The total cost of granite for an L-shaped kitchen = 50 x 100 = Rs.5000/-
4). Marble
Generally,
Marble Required for (Stairs + Porch Area)
Marble required Approx – 450Sqft
Porch (250sqft) + Stairs (200Sqft)
Average market Rate Approx – Rs.50/-Sqft
Total Marble cost – 450 x 50 = Rs.22,500/-
Total Labor Cost For 1000Sqft House Construction
2). Labor cost for house construction…..
Labor rate for construction Approx –Rs.170 to 200/-Sqft
Total built-up area – 1000sqft
Consider, Average labor rate – Rs.180/-sqft
So, Total labor cost – 1000 x 180 = Rs.1,80,000/-
Total Construction Cost – Civil Materials Cost + Finishing Materials Cost + Labor Cost
= 493000 + 58650 + 1,80,000 = Rs.7,31,450/-
EXTRA & VARIABLE COST
1). (a). 2d Plan & Elevation
Average market Rate for 2d plan/ Naksha – Rs.5/-Sqft
Total Area – 1000sqft
Total Cost Approx – 1000 x 5 = Rs.6,000/-
2). Soil/Murrum filling
Approx soil/Murrum quantity – 1500Cft
Soil filling rate approx – 10/-Cft
Total Soil filling cost – 1500 x 10 = Rs.15,000/-
3). Whitewash (Putty/POP)
Thumb Rules,
5 times more than the total area
Total Area – 1000sqft x 5 = 5000sqft
Putty & POP labor rate approx – 3/-Sqft
So, Total labor cost – 5000 x 3 = Rs.15,000/-
Materials costs are also the same – Rs.15,000/-
Total Labor + Materials Cost – Rs.30,000/-
(At this rate contractor apply 2 coats of putty/Pop)
4). Wall Paint
According to thumb rules,
For 1000sqft Area…
Paint surface area – 2500Sqft
Paint labor rate approx – 6/-Sqft
So, Total Painter cost – 2500 x 6 = Rs.15,000/-
Paint materials cost approx – Rs.8 to 10/-sqft
Consider Maximum rate of paint 10/-sqft
Total Paint cost approx – 2500 x 10 =Rs.25,000/-
Total Cost of paint (M+L) = 25,000 + 15,000 = Rs.40,000/-
5). Plumbing
Materials Cost……..
Pvc Pipe cost for underground piping Approx – Rs.9,000/-
CPVC pipe cost approx – Rs.15,000/-
Cost of sanitary items – Rs.35,000/-
Total cost of plumbing materials – 9,000 + 15,000 + 35,000 = Rs.59,000/-
Labor cost for plumbing – Rs.15/-sqft
So, the total labor cost of plumbing for 1000sqft Approx – Rs.15,000/-
So, Total Cost of plumbing (M+L) – 59,000 + 15,000 = Rs.74,000/-
6). Electrical Works
Electrical materials Cost Approx – Rs.25,000/-
(Electrical pipe, conduits, boxes & wires, etc).
2nd cost for switches, lights, fans, Mcb, led approx – Rs.20,000/-
Total materials cost for electrical works – 25,000 + 20,000 = Rs.45,000/-
Electrical works labor cost Approx – Rs.15/-sqft
So, total labor cost for 1000sqft – 1000 x 15 = Rs.15,000/-
Total cost for 1000sqft electrical works (M+L) – 45000 + 15000 = Rs.60,000/-
7). Electricity Consumer Connection
Approx Cost – Rs.5,000/-
These rates vary state to state & city to city.
8). Doors & Window Frame
1 Gate Approx Quantity – 7 + 4 + 7 = 18 Feet
No. of Gate in 2Bhk – 6Nos.
Total Gate Frame Qty – 18 x 6 = 110Feet
1 Window Approx Quantity – 8 x 5 = 40 Feet
No. of Window in 2Bhk – 4Nos.
Total Window Frame Qty – 40 x 4 = 160Feet
Cement Frame Average Rate – Rs.30 – 35/-Feet
Total cost of Frame – 270 x 35 = Rs.9450/-
Labor Cost for installation – Rs.4000/-
Total Cost (M+L) – 9450 + 4000 = Rs.13,450/-
9). Wood Works
4 things are mainly required in-home ( doors + windows +wardrobes + modular kitchen)
Carpenter Rate – 35% of total materials cost
Total Cost of Wood Works Approx – Rs.70,000
Labor cost – 70,000 x 35/100 = Rs.24,500/-
Total cost of wooden works – 70,000 + 24,500 = Rs.94,500/-
10). Main Gate
A 75 kg to 100kg of the main gate is enough
Materials + making charge Approx – Rs.100/-kg
Total cost of Main gate – 100 x 100 = Rs.10,000/-
With Installation charges
11). Septik Tank
A Readymade Single Septik tank is enough
Labor + materials cost Approx – Rs.5,000/-
10). Railing ( for stairs & balcony)
For 1000 sqft house…
Railing quantity required Approx – 30 feet
Railing rate approx – 300 to 350/-feet
Consider the maximum rate – Rs.350/-feet
Total Materials cost – 30 x 350 = Rs.10,500/-
11). Legal permissions & municipal permission – Rs.10,000 to 15,000/-
So, Total Extra Cost – Rs.362950/-
Total Civil works cost – Rs.7,31,450/-
Miscellaneous – Rs.55,000/-
The total construction cost of a 1000sqft house – is Rs.11,49,450 or 11.5 Lakh
Per square feet cost – Total cost / Area
= 11,50,000/1000 = Rs.1150/-
Also, Read
Bar Bending Schedule (BBS) – Basic
Compound wall cost per Rft & Sqft
1000Sqft B – Class House Construction Cost